4.7 GOVERNMENT AGENCIES INVOLVE IN APPROVAL OF PLAN
& BUILDING
• Local Agencies/government (Majlis Bandaraya, Majlis
Perbandaran, Majlis Daerah)
• Town planning
• Environment (JAS)
• Department of Irrigation and drainage (DID)
• Fire Department
• Public Work Department (JKR)
• TNB
• JBA
4.8 FORMS USED IN THE PROCESS OF THE BUILDING PLAN
APPROVAL
(i) Building Plan Application Form
(ii) Form A: Certificate of Buildings/Structural Plans
(For Endorsement on Plans to Be Submitted for Approval)
(iii) Form B: Certificate of Structure
(For Renovation of Existing Structure)
(iv) Form C: Notice of Commencement/Resumption of Building
Operations
(v) Form D: Notice of Completion of Setting Out
(vi) Form E: Notice of Completion of Excavation for Foundations
(vii) Form F: Application for The Issue of Occupation Permit
101