CALCULATIONS,PLOTTING ANDQUESTIONS:

             i.    Draw and plot a graph of force after calibration (Load) against penetration of
             ii.   plunger. Calculate the CBR value for the penetration 2.5mm and 5.0mm.

                  For TOP data
                         CBR2.5 =            ForceforPenetration2.5mm     x   100
                                              13.24 KN (standard force)

                         CBR5.0  =           ForceforPenetration5.0mm     x   100
                                              19.96 KN (standard force)
             For BOTTOM data
                         CBR2.5  =           ForceforPenetration2.5mm      x  100
                                               13.24 KN (standard force)
                         CBR5.0  =           ForceforPenetration5.0mm       x100
                                              19.96 KN (standard force)




             Example of force after calibration (Load) against penetration of plunger graph




                      Load (kN)           Force for Penetration 2.5 mm
                                                       Top

                                                     Bottom


                                                             Penetration of plunger (mm)
                                      2.5



































              Higway Engineering Laboratory                                                                      page      62