                  2.5.2  DISCHARGE BY AGREEMENT (CONSENT/ACCORD BETWEEN

                           PARTIES)

                           ✓ The parties themselves can agree to end the contract, form a

                             new contract, or vary the original one.

                           ✓ Section 63:  novation, rescission (mansuh/batal), alteration.

                           ✓ Section 64:  remission (pemaafan/pelepasan).




                  2.5.3  DISCHARGE BY IMPOSSIBILITY (FRUSTRATION)

                           ✓ A contract automatically comes to an end if it is discharged by

                             frustration that makes performance impossible.

                           ✓ Clause  56:  Effect  of  failure  to  perform  at  fixed  time(time  is

                             essential, time not essential, time other than agreed).

                           ✓ Clause 57: An agreement to do an act impossible in itself is

                             void (afterwards becoming impossible or unlawful).

                           ✓ Instances/condition of frustration:


                             i.  Destruction of subject-matter of contract (that is no fault

                                  of either party & not be a self-induced).

                             ii.  Non-occurrence  of  particular  event  (an  unforeseeable

                                  event).

                             iii.  Death  or  incapacity  of  one  party  where  personal

                                  performance is necessary.

                             iv.  a  change  in  the  law  making  a  previously  legal  contract

                                  illegal.