2.7  The following steps for measuring the face right observation.
                     i.    Loosen the upper clamp and the telescope clamp. Rotate the theodolite

                           circle in a clockwise direction and make sure the vertical circle on the

                           right of the observer. Bisect the station A.
                     ii.   Tighten the upper clamp screw. Point A should be brought into exact
                           coincidence with the point of intersection of the horizontal and vertical

                           cross-hairs by using the vertical circle clamp and tangent screw. The value
                                                                                       o
                           of horizontal angle can be obtained by deducting 180  00’ 00”.
                     iii.  Loosen the upper clamp and set the telescope to bisect station C. Fix the
                           upper clamp and bisect C exactly by using the upper slow motion. Record

                           the C reading.


               2.8  Project : Training of temporary adjustment and measuring horizontal angle

                     measurement


                           Station 1,2, 3 and 4 is the station points fixed on the ground by a pegs.

                            Set a the theodolite over the peg at station 2 and level it accurately.
                           Station 1 and 2 is the  station fixed on the ground by a three ranging

                            rods and plumb.
                           Repeat the process to measure the horizontal angles for station 1, 2,3

                            and 4. The distance for each station to be measured by using a tape.
                           The average  horizontal angle is then obtained by taking the average of

                            two angles obtained with face left and face right.
                           Usually four repetitions of face left and four repetitions of face right

                            should be taken
                           Record the readings and the mean angle should be calculated.



                       Station 1
                                                                                         Station 4







                              Station 2                         Station 3

                                                       Figure :  Closed Traverse