               3.4.2.6  Advantages and Disadvantages of Each Procurement Methods


               3.4.2.7  Advantages  &  disadvantages  of  traditional  procurement
                        method




                                  Advantages                     Disadvantages




                          ▪  It  usually  results  in  high-  ▪  The  client  may  find  it
                            quality work since the client    difficult  to  manage  the
                            has  more  control  over  the    project because they must

                            project; all tenderers create    communicate  with  several
                            a  tender  based  on  the        parties at once.

                            same  information;  and,
                                                          ▪  The  project  will  take  a
                            when      compared      to
                                                             longer  period to  complete.
                            alternative   procurement
                                                             This is because, under the
                            methods,  the  traditional
                                                             traditional   procurement
                            method     is   easier   to
                                                             approach,     the   design
                            implement.
                                                             tender is issued separately

                                                             and the construction tender
                                                             is issued after the design is

                                                             completed; in other words,
                                                             tendering  cannot  begin

                                                             until  the  design  of  the
                                                             project is completed.