3.0 EQUIPMENT
Le-Chateliers Apparatus Water bath Vernier Calliper Balance
4.0 DETAILED PROCEDURE
REFERENCE
WORK PROCESS
DOCUMENT
Weights The permissible variations on weights in use in weighing
the cement shall be as prescribed in Table 1
1. Place the lightly oiled mold on a lightly oiled glass sheet and fill it
with cement paste formed by gauging cement with 0.78 times
the water required to give a paste of standard consistency.
2. Cover the mold with another piece of lightly oiled glass sheet,
place a small weight on this covering glass sheet and
immediately submerge the whole assembly in water at a
temperature of 27 ± 2°C and keep there for 24 hours.
3. Measure the distance separating the indicator points to the
nearest 0.5 mm. Submerge the mold again in water at the
temperature prescribed above.
Higway Engineering Laboratory page 23
31