                        b)  The risks that may develop during the project's delivery and how

                            those risks should be addressed.


                            ➢      The risk connected with the construction project is the

                                   second  factor  that  may  impact  procurement  strategy
                                   selection. Risks are occurrences that may occur during

                                   the  delivery  of  a  building  project,  both  known  and

                                   unknown, and which will usually have a negative impact
                                   on the project's outcomes.


                            ➢      The nature of the project's risks, as well as their impact
                                   on project outcomes if they occur, are frequently dictated

                                   by the project's major objectives and restrictions. Delays
                                   in the construction program, for example, can jeopardize

                                   a project's timely completion.

                              ➢    The risks can be determined once the project's primary

                                   objectives  and  constraints  have  been  outlined.  The
                                   procurement approach used for the project determines

                                   who is responsible for controlling or minimizing specific

                                   risks  in  general.  (For  example,  if  the  procurement
                                   approach  is  "design  and  construct,"  the  risk  of design

                                   flaws is passed to the contractor in broad terms).

                              ➢    As a result, before deciding on a procurement strategy

                                   for a project, departments should think about and figure
                                   out the best way to deal with the identified risks.